Tuesday, 15 November 2016

Westgate Freeway Ramp Closures - 18 November to 16 December

Those of you who enter or exit the Westgate Freeway/Citylink will probably be aware of the works currently being done on both Cook Street (between Todd Road and the eastbound entry/exit from the freeway) and on the westbound entry ramp from Todd Road (the one with the very sharp left hand turn).

It seems that the final stages of this work (expected to be finished by the end of December) will require night (7pm-5am) closures of these roads for profiling, asphalt wearing course and linemarking. Prohasky Street does not seem to be affected by the closures.

Details of the road closures and associated detours (which are rather complex) can be downloaded here.  Allow extra time for the detours or just use Prohasky Street and/or Montague Street rather than Todd Road during this period.

In summary, the closures are:
  • 19-29 November - Cook Street (one carriageway at a time)
  • 27 November to 5 December - westbound (to Geelong) entry ramp from Todd Road
  • 4-15 December - eastbound (from Geelong) exit from freeway
If you have any questions or concerns about the works, please contact Mark Davies, Project Manager, BMD Constructions on 0414 613 338 or email webbdockimprovements@bmd.com.au.