Progress on 103 Beach Street (Foodstore Site)

Since the issuing of a planning permit last November the developer has been preparing plans for endorsement by the City of Port Phillip (CoPP). Plans are expected to be submitted to the CoPP in 3-4 weeks.

The development is for a four-level building comprising a café and supermarket on the ground floor, underground car park and 12 apartments.

Once the CoPP endorses the plans the developer must obtain the consent of Mirvac under the covenants for the site. Pre-selling of apartments will then occur. The building phase is expected to take about 18 months.

The BCNA recently met CoPP staff to discuss improved safety for cyclists, pedestrians and tram users at the eastern edge of the site.